With
the Divine Blessings and grace of our Beloved Swami, the children’s home – Sai
Krushna Mandir – is to be inaugurated on 23rd November, 2012. As
part of this, the SKM construction team is
working to ensure that the architectural drawings, foundation and construction
are all moving along expected timelines. In this March update we share with you
the Front View that has been developed by the expert architects and reviewed by
the SKM Construction Team.
As of now, architectural drawings and soil
testing have been completed. Three point soil testing was done to identify the
depth of foundation needed and estimate the cost and time for foundation. By
Swami’s grace, the hard (solid) part of the ground was reached at a reasonable
depth of approx 2 metres, hence the foundation need not be dug very deep. In the month of March, structural design and
the civil contract will be taken up.